Andorra la VellaThe adaptation of the floors of the cracked building on Avinguda Santa Coloma will last beyond Christmas, according to reports RTVA. Initially, they were supposed to be completed in September, but the delay is explained by two reasons. On the one hand, because the structure had to be reinforced due to the detection of vulnerable areas of the building. On the other hand, the lack of availability of professionals such as locksmiths, painters, etc. have contributed to the fact that the initially planned deadline was not met. It’s been more than a year since a dozen families were evicted from the block due to the risk that the building represented and the intention is that the flats are in good condition so they can return.